WilliamNichols avatar WilliamNichols commented on August 18, 2024

The overhead is not exactly negligible, but is comparable to running a Scrum team. Recording is negligible, teams usually have a single meeting per week of less than an hour, though some have a daily Scrum type short meeting. The meetings are led by the team leader.
The TSP coach is most active during the project launch and post mortem. A launch seems to take about 2 days for a non-trivial project, with another day or two every 2-3 months. It varies somewhat, but these are typical. Figure 1 day of Coach effort at the end of development cycles (typically 2-3 months) for data analysis, 2 days at end of a longer project.

Training is a larger investment, with a most basic developer training taking 5 days, the more advanced requiring 10 days of effort.

from phasedelay.

timm avatar timm commented on August 18, 2024

Thanks for the above. Could I ask that you rephrase this as something I can add to the paper. e.g. references, learned authoritative statements, the usual drill. just add it as issue text and i'll add it in from there.

from phasedelay.

WilliamNichols avatar WilliamNichols commented on August 18, 2024

I can do that. I will get on that this weekend.

From: Tim Menzies [mailto:[email protected]]
Sent: Friday, July 31, 2015 12:03 AM
To: ai-se/phaseDelay [email protected]
Cc: William Nichols [email protected]
Subject: Re: [phaseDelay] is there evidence re the cost of TSP versus anything else? (#21)

Thanks for the above. Could I ask that you rephrase this as something I can add to the paper. e.g. references, learned authoritative statements, the usual drill. just add it as issue text and i'll add it in from there.


Reply to this email directly or view it on GitHubhttps://github.com//issues/21#issuecomment-126561062.

from phasedelay.

WilliamNichols avatar WilliamNichols commented on August 18, 2024

An informed estimate is that tracking time, defects, and tasks requires less then 3% of a developer's time. Weekly team meetings should require at most an hour, which 2.5% of a 40 hour work week. Team launches and replans average about 1 day per month or 5% planning overhead. (Crosstalk,"TSP: Process Costs and Benefits", James McHale, September, 2002, A trained coach can support 4 or 6 teams depending upon team experience.

from phasedelay.

Related Issues (20)

Recommend Projects

  • React photo React

    A declarative, efficient, and flexible JavaScript library for building user interfaces.

  • Vue.js photo Vue.js

    🖖 Vue.js is a progressive, incrementally-adoptable JavaScript framework for building UI on the web.

  • Typescript photo Typescript

    TypeScript is a superset of JavaScript that compiles to clean JavaScript output.

  • TensorFlow photo TensorFlow

    An Open Source Machine Learning Framework for Everyone

  • Django photo Django

    The Web framework for perfectionists with deadlines.

  • D3 photo D3

    Bring data to life with SVG, Canvas and HTML. 📊📈🎉

Recommend Topics

  • javascript

    JavaScript (JS) is a lightweight interpreted programming language with first-class functions.

  • web

    Some thing interesting about web. New door for the world.

  • server

    A server is a program made to process requests and deliver data to clients.

  • Machine learning

    Machine learning is a way of modeling and interpreting data that allows a piece of software to respond intelligently.

  • Game

    Some thing interesting about game, make everyone happy.

Recommend Org

  • Facebook photo Facebook

    We are working to build community through open source technology. NB: members must have two-factor auth.

  • Microsoft photo Microsoft

    Open source projects and samples from Microsoft.

  • Google photo Google

    Google ❤️ Open Source for everyone.

  • D3 photo D3

    Data-Driven Documents codes.