Summary
Paramter & unit |
PyPSA-Eur |
NEP 23 |
NEP 21 |
ACER 23 average |
ACER 23 Q3 |
Vrana & Härtel (2023) |
CIGRE (max) |
CIGRE (min) |
Pathway 2.0 |
AC overhead (€/MW/km) |
442 |
1325-1384 |
736 |
371 |
481 |
- |
250 |
130 |
- |
AC underground (€/MW/km) |
- |
4711 |
3386 |
771 |
821 |
- |
- |
- |
1200 |
AC submarine (€/MW/km) |
- |
- |
- |
1182 |
1488 |
- |
- |
- |
7005 |
DC overhead (€/MW/km) |
442 |
- |
1000 |
371 |
481 |
- |
330 |
180 |
- |
DC underground (€/MW/km) |
- |
3300-3800 |
3250 |
771 |
821 |
870 |
- |
- |
3690 |
DC submarine (€/MW/km) |
1008 |
- |
- |
653 |
741 |
1159 |
1900 |
1270 |
2140 |
DC inverter pair (€/kW) |
166 |
- |
600 |
150 |
193 |
- |
316 |
180 |
- |
NEP 2023
https://www.netzentwicklungsplan.de/sites/default/files/2023-03/230321_NEP_Kostenschaetzung_NEP2037_2045_V2023_1.Entwurf.pdf
auf 2x1.698 GW (2 circuits) = 3396 MW
AC-Freileitung:
380-kV HTLS-Parallelneubau (Doppelleitung, 2 Stromkreise) 4,7 Mio. EUR / km
380-kV Neubau in neuer Trasse (Doppelleitung, 2 Stromkreise) 4,5 Mio. EUR / km
1383.98 EUR/MW/km
1325.09 EUR/MW/km
AC-Erdkabel:
380-kV Neubau in neuer Trasse 16 Mio. EUR / km
4711.43 EUR/MW/km
DC-Erdkabel:
320-kV Neubau in neuer Trasse (1 GW ohne metallischen Rückleiter) 3,5 Mio. EUR / km
525-kV Neubau in neuer Trasse (2 GW mit metallischem Rückleiter) 7,6 Mio. EUR / km
525-kV Neubau in neuer Trasse (2 GW) 6,6 Mio. EUR / km
3500 EUR/MW/km
3800 EUR/MW/km
3300 EUR/MW/km
Assumptions for retrofit suggest similar cost of AC-Freileitung and DC-Freileitung.
Underground assumptions could also be used for submarine assumptions.
NEP 2021
https://www.netzentwicklungsplan.de/sites/default/files/2023-02/NEP_2035_2021_1_Entwurf_Kostenschaetzungen_0.pdf
AC-Freileitung:
380-kV-Neubau Doppelleitung 2,5 Mio. € / km Neubautrasse, Hochstrom
736 €/MW/km
AC-Erdkabel:
Teilverkabelung Neubau
380-kV-Doppelleitung 11,5 Mio. € / km inkl. Kabelübergangsanlage
3386 €/MW/km
DC-Freileitung:
Neubau DC-Freileitung 2,0 Mio. € / km Neubautrasse mit 2 Systemen mit je 2 GW
500 €/MW/km assuming 4GW
DC-Erdkabel:
Neubau DC-Erdkabel 6,5 Mio. € / km Neubautrasse mit 1 x 2 GW
3250 €/MW/km
DC-Konverterstation:
DC-Konverterstation 0,3 Mio. € / MW pro Konverterstation
ACER
https://www.acer.europa.eu/sites/default/files/documents/Publications/ACER_UIC_indicators_table.pdf
Overhead line (million EUR/km) 380-400 kV 2 circuits 1,261 / 1,635
Underground cable (million EUR/km) 300 - 500 kV 1 circuit 1,309 / 1,394
Submarine cable (million EUR/km) AC 2,007 / 2,527- assume 1 circuit?
Submarine cable (million EUR/km) DC 1,108 / 1,258 - assume 1 circuit?
HVDC converters (million EUR/kWh) 0,150 / 0,193 - unit should be MEUR/kW?
average
371.32 EUR/MW/km
770.90 EUR/MW/km
1181.98 EUR/MW/km
652.53 EUR/MW/km
150000 EUR/MW
Q3 values
481.44 EUR/MW/km
820.97 EUR/MW/km
1488.22 EUR/MW/km
740.87 EUR/MW/km
193000 EUR/MW
Langfristszenarien
https://www.langfristszenarien.de/enertile-explorer-wAssets/docs/Consentec-TUBER_BMWK_LFS3_Webinar_Netze_T45_final_v2.pdf
"Kostenansätze entsprechend ÜNB-Annahmen im NEP bzw. Erfahrungswerten Consentec"
TYNDP
TYNDP not published, at least nowhere to be found ?!
DEA
only has distribution level assumptions, no transmission level
Vrana / Härtel
https://pdf.sciencedirectassets.com/271091/1-s2.0-S0378779617X00072/1-s2.0-S0378779617302572/dx.doi.org/10.1016/j.epsr.2017.06.008
https://doi.org/10.1109/EEM58374.2023.10161832
OverHead Lines (OHL) are not included in the new cost
model, as only a few HVDC overhead lines are being built
or planned in Europe
Rating of 2.2 GW
submarine:
1.061 M€/GW/km
2.784 M€ assuming 2.2 GW and 100km length
0.248 M€/km / 2.2 GW
1061 €/MW/km + 112.72 €/MW/km + 12.65 €/MW/km = 1159.37 €/MW/km
underground
0.672 M€/GW/km
2.784 M€ assuming 2.2 GW and 100km length
0.408 M€/km / 2.2 GW
672 €/MW/km + 185.45 €/MW/km + + 12.65 €/MW/km = 870.1 €/MW/km
technology-data
HVAC overhead investment 442.1414 EUR/MW/km
HVDC overhead investment 442.1414 EUR/MW/km
HVDC submarine investment 1008.2934 EUR/MW/km
HVDC inverter pair investment 165803.0398 EUR/MW
Pathway 2.0 Techno-economic data
https://zenodo.org/records/10101328
CIGRE
(e-mail Strommarkttreffen)
https://groups.io/g/strommarkttreffen/message/5721
globaler Wertebereich
|
Cost (M€) |
DC OHL (M€/km/GW) |
DC USC (M€/km/GW) |
AC OHL (M€/km/GW) |
AC/DC Converter (M€/GW for one SS) |
AC/AC Back to Back SS (M€/GW for one SS) |
Max |
0.33 |
1.90 |
0.25 |
158 |
158 |
158 |
Min |
0.18 |
1.27 |
0.13 |
90 |
90 |
90 |